How does the wind at Jeffreys Bay wind farm reach the grid?
Drive along the N2 west of Jeffreys Bay and you see sixty white turbines on the hills. You don't see the rest of the journey: the cables under the farm roads, the substation that raises the voltage, the 132 kV line on its poles and the Eskom substation where the power joins the wider network. A flat map shows that chain as dots and lines. In three dimensions it starts to look like the real thing.
Day 27 of the 30 Day Map Challenge is A new tool. My new tool is the 3D functionality coming in Icon Map Pro: glTF models placed and animated from data, and lines drawn with real heights. I wanted a subject that needs both, so I followed one wind farm's electricity from turbine to grid. It also closes a loop with Day 2, where I mapped South Africa's power lines.
Explore the interactive report
- Date and Time: pick any hour of 19–25 September 2025. The turbines turn to face that hour's wind, spin at an illustrative speed and take the colour of their operating state. The four cards show the estimated output, its share of the 138 MW capacity, the operating state and the wind at 100 m.
- Tilt, turn and zoom. The map opens on a tilted view of the whole connection, over terrain. Zoom in and the turbines, towers, substations and raised wires appear as 3D models.
- Explore the infrastructure: a multi-select list. Generation shows all turbines and collector cables, or one of six feeders; Transmission shows the line from the wind farm to Melkhout, or every transmission line drawn in 3D; Substations flies to one substation.
- The chart shows the week's estimated output, with a dashed line at the 138 MW installed capacity and a black line at the hour you picked.
- Card labels on the wind farm and both substations follow the hour, for example Jeffreys Bay potential output: 138 MW (modelled) on Melkhout.
Interactive report: Day 27, New Tool
What it doesn't show: metered output, the real cable routes or the real equipment layout inside either substation. The map's subtitle says so, the legend marks the collector routes as illustrative, and I'll say which parts are mapped, modelled or illustrative as I go.
Starting with OpenStreetMap
Everything you can see on the ground comes from the OpenStreetMap extract for South Africa (Geofabrik, 30 October 2026), read with DuckDB's ST_ReadOSM. OSM has all 60 Jeffreys Bay turbines, matching Globeleq's count, in a wind farm site relation, so I could pick them out by membership rather than by drawing a box.
The connection took some detective work. The farm substation isn't named in OSM, but its outline is tagged 132 kV, and two short line stubs loop it into a longer 132 kV line. Followed west, that line runs 5.7 km to Melkhout Substation, a 132/66 kV substation outside Humansdorp, where seven other circuits also arrive. OSM even maps the gantries where some of those lines end inside Melkhout's fence, so the 3D bays could sit where the real ones are.
Checking the map against the documents
OSM gave me the geometry; three documents confirmed what it means. A Kouga Municipality report (February 2026) names the farm substation Sunnyside and describes the 132 kV connection to Melkhout. An Eskom environmental management programme for a battery project at Melkhout (2019) lists Jeffreys Bay Wind Farm among the facilities that supply the substation. And ADM Engineers' project page for the farm's protection scheme describes a 33 kV internal collection system and the 132 kV Eskom connection. So the voltages on the map are sourced; only the cable routes are not.
One caution from the series runs through this map too: OSM isn't always complete. Four distribution lines stop at poles 145–215 m short of Melkhout. They probably go underground for the last stretch, but nothing is mapped, so I left them as OSM has them.
Starting with ERA5 wind
The wind is ERA5, the Copernicus reanalysis, as an hourly time series of 100 m wind at the farm (DOI 10.24381/1cf1ad76). I downloaded a long window and ranked candidate weeks by how much story each told: calm hours, full-power hours and a good spread of wind directions. 19–25 September 2025 won.
ERA5 gives one value for the whole farm, so all sixty turbines share one wind each hour. The 100 m wind is a proxy for the 80 m hub height. It's modelled, not measured at the turbines.
From wind to megawatts
To turn wind into output I needed a power curve for the Siemens SWT-2.3-101, and Siemens doesn't publish one as numbers. The Open Energy Platform turbine library lists the model without a curve, but it has the power coefficients of its sister turbine, the SWT-2.3-113. I applied those to the 101 m rotor up to 8 m/s, then rose smoothly to the 2,300 kW rating at 12 m/s, with nothing below the 4 m/s cut-in or above the 25 m/s cut-out.
I checked it against the manufacturer's own curve, and the simplified curve is within 4.7% of rated power at every wind speed, and the week's energy is within 1.2%.
Bringing turbines to life with 3D models
The turbine is a CC0 model from Tevy, rebuilt with gltf-transform into a real-size GLB: 80 m hub, 101 m rotor and a 60-second rotor-spin clip. I also removed the vertex colours, which had painted dark bands up the tower. The turbine model is hosted in Azure blob storage and DAX measures set the model, its heading (into the hour's wind) and its animation speed. The clip turns once a minute, so the rotor's rpm doubles as the playback speed.
The towers are Icon Map's built-in monopole and lattice tower, scaled to typical 132 kV heights, and each faces along its line.
Raising the wires with Z heights
This is the part I was most curious about. Shapes from data now reads LINESTRING Z, and with Use Z heights switched on, the third number is a height above the ground. Each conductor is a WKT line through the arm tips of its supports, with a little sag added between them. That's 84 conductors: the route to Melkhout, the line east through the farm, a double-circuit lattice line, the last span of four other lines, and every busbar and bay connection inside both substations.
Measuring the models first
My first wires missed the poles, because I'd guessed where the crossarms were. The fix was to measure the models. Slicing the meshes by height gave me the insulator ends: on the monopole at 23.0, 19.5 and 16.0 m.
Two rules then made the wiring consistent:
- Tie the arms to the map, not the drawing direction. A single-circuit line on a two-sided pole is staggered: top and bottom phases on one side, the middle phase on the other. I first chose the side relative to the direction I'd traced each line, and two stubs traced in opposite directions used opposite arms. Now the two-phase side always faces north-east.
Drawing every line once
The wider grid comes from Day 2's approach, as a PMTiles catalog layer: 1,784 Eastern Cape power lines, about 10,100 km, in a 2.3 MB file on Azure, coloured by voltage band. Wherever the report draws a line in 3D, the tiles cut it out, 16.5 km in 10 stretches, so no line appears twice, once on the ground and once in the air.
Building substations from catalog parts
Neither substation's equipment is mapped, so both are representative layouts from Icon Map catalog models: line-entry gantries, surge arresters, current transformers, breakers, power transformers, kiosks and a control building, 111 parts in all. Each yard has straight busbars on plain gantry beams, line bays at right angles to them, and transformers between the buses. Melkhout's bays face the side their lines come from. Every footprint is checked against the OSM outline and kept at least 2 m inside the fence.
At the wind farm, the substation is where the 33 kV collector network ends. Those cables are underground and their routes aren't published, so I drew six illustrative feeders of ten turbines each along the farm's mapped roads and tracks: about 77 km of cable route, in deep teal on the surface.
Designing for the journey
- One colour per job. Turbines use the four operating-state colours, the 132 kV connection Day 2's orange and the collector cable routes a deep teal. A two-line legend over the map names the teal and orange lines and marks the routes as illustrative. The Operating state card is written in its own state colour.
- 3D from the first view. The map opens tilted over terrain, so the subtitle's promise of three dimensions is kept before anyone clicks.
- Tight frames for the substations. The Substations options show only the yard, so auto-zoom flies right into it.
- Honest labels. The map's subtitle says the 3D models, cable routes and equipment layouts are illustrative, the cards say estimated and modelled, and the substation cards say layout illustrative.
- A chart that knows the hour. The Date and Time slicers sit on a small disconnected copy of the hours, so the chart keeps the whole week and marks the selected hour with a reference line.
What the map reveals
A windy week, unevenly spread. The farm's estimated output for the week is about 7,700 MWh, a 33% capacity factor. Monday alone produced about 2,600 MWh, while Thursday produced only about 35 MWh.
Full power is rare. The farm reached its full 138 MW in just 11 of the 168 hours, and it was below cut-in for 47. The rest of the time it was somewhere in between, which is exactly what the chart's shape shows.
Melkhout is the hub. Jeffreys Bay's 5.7 km line is one of eight circuits into Melkhout: six at 132 kV and two at 66 kV. Seen in 3D, the substation explains itself, with lines arriving from every side.
A caution: these are estimates of what the turbines could generate from one modelled wind value. They exclude wakes, electrical losses, curtailment and downtime, so they aren't what Melkhout actually received.
What I learned from Day 27
- Measure before you wire. Guessed attachment points look wrong immediately in 3D. Ten minutes slicing the models saved hours of nudging.
- Make rules depend on the map, not on your code. Arms chosen relative to the drawing direction looked random; arms fixed to the compass looked engineered.
- Make the physics agree. A rated wind speed in one table and a power curve in another will eventually contradict each other on screen.
- Less in a view frames better. Auto-zoom fits everything in the view, so every extra row moves the camera.
Final thoughts
The new tool turned a schematic into something you recognise. The same pattern works for any network you manage, such as pipelines, telecoms masts or a factory floor. Draw the mapped assets from data, build what isn't mapped from catalog parts and say so, and give the wires their real heights. Power BI data then drives the turning, the colours and the numbers.
Pick Monday at 06:00, then zoom in on Melkhout.
Sources and attribution
- Infrastructure: © OpenStreetMap contributors, ODbL. Geofabrik South Africa extract, 30 October 2026: turbines, the wind farm site relation, power lines, towers, portals, substation outlines, roads and tracks. https://www.openstreetmap.org/copyright
- Electrical network: Kouga Municipality (February 2026), https://www.kouga.gov.za/download/6871, p. 163, section 2.5.1.2 (the 132 kV connection between Sunnyside and Melkhout); Eskom (2019), Melkhout BESS Environmental Management Programme, p. 4, section 3 (Jeffreys Bay Wind Farm among the facilities supplying Melkhout Substation); ADM Engineers, Jeffreys Bay Wind Farm protection scheme, https://adm-eng.com/ourprojects/jeffreys-bay-wind-farm-protection-scheme/ (33 kV internal collection system and 132 kV Eskom connection).
- Wind farm and turbines: Globeleq, Jeffreys Bay Wind Farm, https://globeleq.com/power-plants/jeffreys-bay/ (60 turbines, 138 MW); Siemens SWT-2.3-101 specifications, with Herbst (2015).
- Wind: Copernicus Climate Change Service (2025): ERA5 hourly time-series data on single levels from 1940 to present. C3S Climate Data Store. DOI: 10.24381/1cf1ad76. Accessed 25 November 2026. Contains modified Copernicus Climate Change Service information 2025; neither the European Commission nor ECMWF is responsible for any use that may be made of the Copernicus information or data it contains.
- Power curve: power coefficients of the SWT-2.3-113 from the Open Energy Platform turbine library (openenergyplatform.org), checked against Siemens AG (2010), SWT-3.0-101: An example of Systems Engineering, p. 8. The Siemens values are not reproduced.
- 3D models: Tevy wind turbine v2 (CC0, tevy.dev); Icon Map built-in towers; Icon Map catalog substation models (CC0, Tekantis).
- Grid tiles: Eastern Cape power lines from OpenStreetMap, built with tippecanoe as PMTiles.
Methodology note: Turbine, line, tower and substation positions are mapped in OpenStreetMap; the 33 kV and 132 kV voltages and the connection to Melkhout are from the Kouga Municipality, Eskom and ADM Engineers documents above. Wind is ERA5 100 m reanalysis at the farm centroid, one value for all 60 turbines, used as a proxy for the 80 m hub. Estimated output comes from a simplified power curve (SWT-2.3-113 power coefficients on the 101 m rotor to 8 m/s, then a smooth rise to 2,300 kW at 12 m/s, with 4 m/s cut-in and 25 m/s cut-out), within 4.7% of rated power of the Siemens curve. It excludes wakes, losses, curtailment and availability. Operating states and rotor speeds use the same thresholds and are illustrative. Tower heights are typical values (25 m monopole, 30 m lattice). Collector cable routes and feeder groups follow the farm's mapped roads and are illustrative. Substation equipment layouts are representative and placed inside the mapped outlines. Conductor heights come from the measured attachment points of the 3D models, with 2.5% sag on line spans.